What must happen to a SWM facility before a permit can be terminated?

Prepare for the Virginia DEQ SWM Inspector Test with our comprehensive study material. Delve into multiple-choice questions and gain access to valuable hints and explanations. Stay ahead in your exam preparations with confidence!

Before a stormwater management (SWM) permit can be terminated, it is essential that all inspections have been passed. This requirement ensures that the SWM facility meets the established standards for design, construction, and functionality. Passing inspections confirms that the facility operates as intended and effectively manages stormwater according to regulatory requirements.

Successful completion of inspections serves as a quality assurance measure, validating that the facility is constructed properly and is functioning as per the prescribed design specifications. It helps to mitigate potential issues related to stormwater runoff, erosion, and sediment control that could arise if the facility were to be released without verification of compliance.

Other options, although important in the lifecycle of a SWM facility, do not reflect the direct prerequisite for permit termination. For example, while all construction must be complete and adequate documentation submitted, these steps do not hold the same weight as the necessity for successful inspections, which serve as direct proof of compliance with local and state standards. Therefore, the focus on passing all inspections is vital for ensuring both public safety and environmental protection prior to the termination of a SWM permit.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy